Custom Engineered Upgrades: Step-By-Step Process

1 2 3 4 5 6 7 8 9 10111213141516171819202122232425262728

Week 1 • Enter Job into system • Create schedule

• Get Information from the field • Determine need for site visit Weeks 2-3 • System Information collected Weeks 4-6 • System designed Week 7 • Submittals created • Submittals given to customer Weeks 8-10 • Submittals approved, returned Weeks 11-12 • Design finalized • Purchase orders generated

• Parts ordered Weeks 13-14 • Job kitted Weeks 14-18

• Job built Week 19

• Job tested 20th week

• Job shipped Weeks 22-24 • As-built sent to field personnel Weeks 24-26 • System installed • As-installed prints returned Weeks 26-28 • OEM manuals created, shipped • Close project